Applied Digital Ellendale AI Campus
1 / 1
AI Data Center Campus

Applied Digital Ellendale AI Campus

Investment: N/A
Ellendale, ND, Ellendale, Dickey County, North Dakota, United States
Project Status Under Construction / Leasing
Capacity (MW) 250
Developer Applied Digital
AI cloud and accelerated computing Tenant: CoreWeave Nuclear: None publicly stated

Project Description

Applied Digital announced a 250 MW AI data center lease with CoreWeave at its Ellendale campus.

Data Center Specifications

Planned Capacity (MW)
250
Announced Investment
N/A
Campus Size (Acres)
N/A
Facility Area (Sq Ft)
N/A
Developer / Owner
Applied Digital
Operator / Tenant
CoreWeave
Construction Start
Under construction
Estimated Completion
First 100 MW expected Q4 2025
Construction Jobs
N/A
Operational Jobs
N/A

Power Strategy & Energy Integration

Power Strategy
Energy-efficient campus leveraging regional climate and available energy
Utility / Energy Partner
Regional energy partners
Nuclear Relationship
None publicly stated
AI Workload & Use Case
AI cloud and accelerated computing

Project Diligence & Capabilities

Project Details The first 100 MW building was expected to be ready for service in the fourth quarter of 2025.
What Project Has Constructing campus, signed tenant and stated capacity.
What Project Needs Remaining phased delivery, power reliability and commissioning.
Verification Confidence High
Last Verified 2026-08-05

Data Center Gallery

Contact Representative

Applied Digital
Developer / Operator
Send Inquiry
Inquire About This Data Center
Get in touch with our AI Data Center infrastructure team

Quick Facts

  • Planned Capacity 250
  • Investment N/A
  • Campus Acres N/A
  • Square Feet N/A
  • Nuclear Partner None publicly stated
  • Target Completion First 100 MW expected Q4 2025

Source References

Location Map

Ellendale, ND, Ellendale, Dickey County, North Dakota, United States

Similar Data Centers